Infrastructure Analytical Dashboard

Value for Money.

Time and cost overrun analysis

Budget vs Completion Cost
46.29M
Difference between approved project budget and completion cost GHS 46,292,394.90
Contract Price vs Completion Cost
3.10M
Difference between contract price and completion cost GHS 3,103,773.92
Time Overruns

Proportion of projects completed later than the planned contract end date

  • Time overrun 24.19%
  • Completed on time 75.81%
By Funding Source

Top 5 funding sources with time overrun

  • DACF - RESPONSIVENESS FACTOR GRANT 8 projects
  • DISTRICT ASSEMBLIES COMMON FUND 2 projects
  • AGENCE FRANÇAISE DE DÉVELOPPEMENT 1 project
  • EUROPEAN UNION (EU) 1 project
  • MINERALS DEVELOPMENT FUND 1 project
Cost Overruns

Proportion of projects with completion cost above the contracted total

  • Cost overrun GHS 11,002,770.70
  • Within contract value 56 projects
By Funding Source

Value of cost overrun by funding source

  • WORLD BANK GHS 8,805,407.22
  • DACF - RESPONSIVENESS FACTOR GRANT GHS 2,153,707.04
  • EUROPEAN UNION (EU) GHS 36,256.30
  • AGENCE FRANÇAISE DE DÉVELOPPEMENT GHS 0.05
  • MINERALS DEVELOPMENT FUND GHS 0.05
Five Years to 2027

Contract price vs completion cost of completed projects, by completion year

Top 5 Contractors with Cost Overrun

Contracted total (navy) and the overrun portion (red)