Project Identification
- Project Reference Number
- WR/AWMA/WKS/UNCDF/29/2025
- Project Name
- Construction of a Gari processing Factory
- Sector
- Housing & Buildings
- Project Type
- New Construction
- Project Location
- Western Region
- Purpose
- Enhances cassava value addition, creates jobs, boosts local economy, and reduces post-harvest losses
- Project Description
- Gari processing factory with processing equipment, storage, and office facilities to promote cassava value addition and local employment
Project Preparation
- Project Scope
- Construction of factory building, installation of processing equipment, utilities, and site clearance
- Environmental Impact
- B/C Moderate environmental impact; dust, noise, and cassava waste managed responsibly
- Land and Settlement Impact
- None—the project is on municipal land with no displacement
- Design Standard
- Ghana Building Code, LGWD, and Food Processing/Industrial standards
- Expected Life of Asset
- 25–30 years for the building; 10–15 years for machinery (with maintenance)
- Risk Assessment
- Risks: Delays, cost overruns, H&S, machinery, environmental, compliance
Mitigation: Monitoring, safety, testing, inspections
- Funding
-
European Union (EU)
Donor / Development Partner
GHS 599,921.02
- Project Budget
- GHS 599,921.02
- Project Budget Approval Date
- Mon Dec 08 2025
Project Completion
- Project Status
- Completed
- Completion Date
- Thu Jul 09 2026
- Scope at Completion
- Building completed, utilities functional, machinery operational, site handed over