Home / Projects / Completion of the Community Center
Social Services Completed

Completion of the Community Center

Completion of the Fasin Community Center, including structural, finishing, electrical, and plumbing works to make the facility fully functional.

Western Region WR/AWMA/DACF/MP/WKS/NCT/24/2024 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Social Services
Location
Western Region
Stage
Completion
Contracting Entity
Ahanta West Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 295,456.00
MP’s Common FundGHS 295,456.00
Final CostGHS 286,696.00
Project Identification
Project Reference Number
WR/AWMA/DACF/MP/WKS/NCT/24/2024
Project Name
Completion of the Community Center
Sector
Social Services
Project Type
New Construction
Project Location
Western Region
Purpose
Provides a venue for social, cultural, and administrative activities Enhances community engagement and local development Creates temporary employment during construction
Project Description
Completion of the Fasin Community Center, including structural, finishing, electrical, and plumbing works to make the facility fully functional.
Project Preparation
Project Scope
Completion of remaining structural works Roofing, ceiling, and floor finishes Electrical and plumbing installations Doors, windows, and internal fittings External works, including site clearance and landscaping Provision of necessary furniture and fixtures
Environmental Impact
EPA Category: C – Minimal environmental impact Confined to the existing site, limited dust, noise, and construction waste No significant long-term environmental effects expected
Land and Settlement Impact
No land acquisition or resettlement required Works confined within the allocated site footprint
Design Standard
Built according to Ghana Building Code, local government standards, and applicable British/International Standards
Expected Life of Asset
25–30 years post-completion, assuming routine maintenance and proper use.
Risk Assessment
Construction delays, cost overruns, H&S hazards, environmental impacts, and regulatory non-compliance Close supervision, financial controls, safety protocols, environmental management, and compliance inspections
Funding
MP’s Common Fund District Assemblies Common Fund (DACF)
GHS 295,456.00
Project Budget
GHS 295,456.00
Project Budget Approval Date
Thu Jun 06 2024
Project Completion
Project Status
Completed
Completion Cost
GHS 286,696.00
Completion Date
Mon Nov 17 2025
Scope at Completion
The project will be considered complete when: All structural and finishing works are executed per approved drawings Electrical and plumbing systems are fully installed and functional Furniture and fixtures are installed Site cleared and handed over with as-built documentation

Questions about this project?

This project is disclosed by Ahanta West Municipal Assembly. Citizens have the right to ask questions about public infrastructure.