Home / Projects / Construction of double seal bituminous 0...
Transport & Roads Completed

Construction of double seal bituminous 0.6km of Damtse with side drains

Western Region WR/AWMA/GSCSP/UDS-3/WKS/NCT/09/LOT 1/2023 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Transport & Roads
Location
Western Region
Stage
Completion
Contracting Entity
Ahanta West Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 4,552,108.22
SECONDARY CITIESGHS 4,552,108.22
Contract (USD)USD 389,401.90
Final CostGHS 4,552,108.22
Project Identification
Project Reference Number
WR/AWMA/GSCSP/UDS-3/WKS/NCT/09/LOT 1/2023
Project Name
Construction of double seal bituminous 0.6km of Damtse with side drains
Sector
Transport & Roads
Sub sector
Roads
Project Type
New Construction
Project Location
Western Region
Purpose
improve economic activity
Project Description
Construction of double seal bituminous 0.6km of Damtse with side drains
Project Preparation
Project Scope
Construction of road and side drains
Environmental Impact
facilitate free flow of water and vehicles
Land and Settlement Impact
improve economic activities
Design Standard
Ghana Urban Roads
Expected Life of Asset
25
Risk Assessment
n/a
Funding
SECONDARY CITIES Donor / Development Partner
GHS 4,552,108.22 (original amount 389,404.90, currency unrecorded)
Project Budget
GHS 4,552,108.22
Project Budget Approval Date
Thu Sep 28 2023
Tender Management

Initiation

Procuring Entity
Ahanta West Municipal Assembly
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 4,552,108.22
Award Date
Tue Apr 08 2025
Award Criteria
All documents required for award of contract were provided

Contracting

Contract Type
Works
Contract Title
Construction of road and side drains at Damtse
Contract Identification
WR/AWMA/GSCSP/UDS-3/WKS/NCT/09/LOT 1/2023
Contract Price
USD 389,401.90
Contract Scope of Work
road with side drains
Contract Start Date
Thu Sep 28 2023
Contract Duration
From: Thu Sep 28 2023
To: Sat Sep 28 2024
In Days: 366
#Name of FirmRole
1 BUDOX CONSTRUCTION COMPANY LIMITED Lead Contractor
Contract Status
Active
Contract Implementation

Site Photos

Project Completion
Project Status
Completed
Completion Cost
GHS 4,552,108.22
Completion Date
Sat Sep 28 2024
Scope at Completion
construction of road and side drains

Questions about this project?

This project is disclosed by Ahanta West Municipal Assembly. Citizens have the right to ask questions about public infrastructure.