Project Identification
- Project Reference Number
- —
- Project Name
- Construction of Fire Service Station at Mpohor
- Sector
- Housing & Buildings
- Project Type
- New Construction
- Project Location
- Western Region
- Project Description
- Construction of Fire Service Station at Mpohor
Project Preparation
- Project Scope
- Planned project corresponds with executed project and there were no variations.
- Environmental Impact
- The facility does not pose any threat to the environment as certified by the EPA
- Land and Settlement Impact
- There are no issues with the land and also, location does not disrupt the built environment
- Design Standard
- The design of the facility meets required standards
- Expected Life of Asset
- 50 years
- Funding
-
DACF - Responsiveness Factor Grant
District Assemblies Common Fund (DACF)
GHS 535,446.98
- Project Budget
- GHS 535,446.98
- Project Budget Approval Date
- Mon Sep 05 2022
Project Completion
- Project Status
- Completed
- Completion Cost
- GHS 535,446.98
- Completion Date
- Wed Sep 25 2024
- Scope at Completion
- Completed and in use
Questions about this project?