Home / Projects / Construction Of 10no. Refuse Collection...
Water & Sanitation Completed

Construction Of 10no. Refuse Collection Points And Fabrication Of 10no Containers

Western Region WR/EKMA/GSCSP/UDG-2/WKS/NCT/002/LOTS/2020 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Water & Sanitation
Location
Western Region
Stage
Completion
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 1,786,353.58
World BankUSD 308,742.56
ContractGHS 1,885,695.00
Final CostGHS 10,182,215.50
Project Identification
Project Reference Number
WR/EKMA/GSCSP/UDG-2/WKS/NCT/002/LOTS/2020
Project Name
Construction Of 10no. Refuse Collection Points And Fabrication Of 10no Containers
Sector
Water & Sanitation
Project Type
New Construction
Project Location
Western Region
Project Description
CONSTRUCTION OF 10NO. REFUSE COLLECTION POINTS AND FABRICATION OF 10NO CONTAINERS
Project Preparation
Project Scope
CONSTRUCTION OF REUFSE COLLECTION POINT, FABRICATION OF SKIP CONTAINERS
Expected Life of Asset
25 YEARS
Funding
World Bank Donor / Development Partner
USD 308,742.56 (GHS 1,786,353.58 at time of funding)
Project Budget
GHS 1,786,353.58
Project Budget Approval Date
Tue Apr 20 2021
Tender Management

Initiation

Procuring Entity
Effia-Kwesimintsim Municipal Assembly
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
4
Cost Estimate
GHS 2,100,000.00

Contracting

Contract Type
Works
Contract Title
Construction Of 10no. Refuse Collection Points And Fabrication Of 10no Skip Containers
Contract Identification
WR/EKMA/GSCSP/UDG-2/WKS/NCT/002/LOTS/2020
Contract Price
GHS 1,885,695.00
Contract Scope of Work
Construction of Refuse collection Points, Fabrication of skip containers
Contract Start Date
Wed May 26 2021
Contract Duration
From: Wed May 26 2021
To: Wed Nov 30 2022
In Days: 553
#Name of FirmRole
1 Asabea Engineering Limited Lead Contractor
Contract Status
Active
Project Completion
Project Status
Completed
Completion Cost
GHS 10,182,215.50
Completion Date
Mon May 30 2022
Scope at Completion
100% COMPLETE

Questions about this project?

This project is disclosed by Effia-Kwesimintsim Municipal Assembly. Citizens have the right to ask questions about public infrastructure.