Home / Projects / Construction Of 1no. Mechanized Borehole...
Housing & Buildings Completed

Construction Of 1no. Mechanized Borehole At Tumentu

Construction of 1No. Mechanized Borehole

Western Region WR/NEMA/WKS/DDF/RFG/03/2021 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Housing & Buildings
Location
Western Region
Stage
Completion
Contracting Entity
Nzema East Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 32,000.00
DACF - Responsiveness Factor GrantGHS 32,000.00
ContractGHS 32,000.00
Final CostGHS 32,000.00
Project Identification
Project Reference Number
WR/NEMA/WKS/DDF/RFG/03/2021
Project Name
Construction Of 1no. Mechanized Borehole At Tumentu
Sector
Housing & Buildings
Sub sector
Residential Housing
Project Type
New Construction
Project Location
Western Region
Purpose
To provide a reliable source of drinking water
Project Description
Construction of 1No. Mechanized Borehole
6 Clean Water and Sanitation
Project Preparation
Project Scope
Construction of 1No. Mechanized Borehole
Land and Settlement Impact
To improve their living condition
Design Standard
National building code
Expected Life of Asset
20yeras
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 32,000.00 (original amount 5,565.22, currency unrecorded)
Project Budget
GHS 32,000.00
Project Budget Approval Date
Tue Apr 06 2021
Tender Management

Initiation

Procuring Entity
Nzema East Municipal Assembly
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 32,000.00

Contracting

Contract Type
Consultancy
Contract Title
Construction of 1no. Mechanized Borehole At Tumentu
Contract Identification
WR/NEMA/WKS/DDF/RFG/03/2021
Contract Price
GHS 32,000.00
Contract Scope of Work
Construction of 1no. Mechanized Borehole
Contract Start Date
Tue Apr 06 2021
Contract Duration
From: Tue Apr 06 2021
To: Sun Apr 25 2021
In Days: 19
Contract Status
Active
Project Completion
Project Status
Completed
Completion Cost
GHS 32,000.00
Completion Date
Wed May 19 2021
Scope at Completion
Construction of 1No. Mechanized Borehole

Questions about this project?

This project is disclosed by Nzema East Municipal Assembly. Citizens have the right to ask questions about public infrastructure.