Home / Projects / Construction of 1 No 3 – Unit Classroom...
Education Completed

Construction of 1 No 3 – Unit Classroom Block with Ancillary Facilities

Construction of 1-No 3 – Unit Classroom Block with Ancillary Facilities

Western Region AWMA/DDF/EDU/2018/02 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Education
Location
Western Region
Stage
Completion
Contracting Entity
Ahanta West Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 242,285.32
DACF - Responsiveness Factor GrantGHS 242,285.32
ContractGHS 417,226.96
Final CostGHS 242,285.32
Project Identification
Project Reference Number
AWMA/DDF/EDU/2018/02
Project Name
Construction of 1 No 3 – Unit Classroom Block with Ancillary Facilities
Sector
Education
Project Type
New Construction
Project Location
Western Region
Purpose
Increase enrolment and access to quality education
Project Description
Construction of 1-No 3 – Unit Classroom Block with Ancillary Facilities
Project Preparation
Project Scope
Substructure, Block Work, Concrete Works, Carpentry and Joinery, Roof Covering, Iron Mongery, Metal Works, Finishing, Electrical Work and Painting and Decorating, Aprons, drains and ramp
Environmental Impact
Erosion control
Land and Settlement Impact
Increase accessibility and quality education
Design Standard
National Building Regulation 1996 LI 1630 and Ghana Building code
Expected Life of Asset
25 Years
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 242,285.32 (original amount 55,064.85, currency unrecorded)
Project Budget
GHS 242,285.32
Project Budget Approval Date
Wed Oct 04 2017
Tender Management

Initiation

Procuring Entity
Ahanta West Municipal Assembly
Procurement Process
2 Stage (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
4
Cost Estimate
GHS 417,226.96

Contracting

Contract Type
Works
Contract Title
Construction Of 1-No. 3-Unit Classroom Block.
Contract Identification
WR/AWMA/WKS/002/2022
Contract Price
GHS 417,226.96
Contract Scope of Work
1. Substructure 2. Block Work 3. Carpentry and Joinery 4. Roof Covering 5. Finishing 6. Electrical Work 7. Painting and Decorating 8. Borehole Drilling, Mechanization 9. Concrete Stand and Poly Tank 10. Four-Seater water closet toilet
Contract Start Date
Mon Oct 24 2022
Contract Duration
From: Mon Oct 24 2022
To: Wed Mar 01 2023
In Days: 128
#Name of FirmRole
1 1st Class Construction And Electricals Limited Lead Contractor
Contract Status
Active
Contract Implementation

Variations to Contract

Other on Wed Jul 06 2022
Why: No change

Funds Disbursed

Disbursed: GHS 0.00 Contract value: GHS 417,226.96
Project Completion
Project Status
Completed
Completion Cost
GHS 242,285.32
Completion Date
Thu Sep 05 2019
Scope at Completion
Substructure, Block Work, Concrete Works, Carpentry and Joinery, Roof Covering, Iron Mongery, Metal Works, Finishing, Electrical Work and Painting and Decorating, Aprons, drains and ramp

Questions about this project?

This project is disclosed by Ahanta West Municipal Assembly. Citizens have the right to ask questions about public infrastructure.