Project Identification
- Project Reference Number
- WR/EKMA/GSCSP/UDG-1/WKS/NCT/002/2020
- Project Name
- Construction Of Storm Drain From Kojo Kumi Avenue, Kwesimintsim Total Filling Station And Kwesimintsim
- Sector
- Transport & Roads
- Sub sector
- Roads
- Project Type
- New Construction
- Project Location
- Western Region
- Purpose
- Prevent Flooding of the Community
- Project Description
- Construction of Storm Drain From Kojo Kumi Avenue, Kwesimintsim Total Filling Station and Kwesimintsim with Pedestrain Foofbridge
Project Preparation
- Project Scope
- Storm Drain (510 x 6 x 1.5m) Rectangular, Pedestrian Foot Bridge
- Environmental Impact
- Facilitate Free Flow of Water to Prevent Flooding of the Community
- Land and Settlement Impact
- Facilitate Free Flow of Water to Prevent Flooding of the Community
- Design Standard
- National Building Regulation 1996 LI 1639 Ghana Building Code
- Expected Life of Asset
- 25 years
- Risk Assessment
- none
- Funding
-
World Bank
Donor / Development Partner
USD 605,481.00
(GHS 3,297,752.30 at time of funding)
- Project Budget
- GHS 3,297,752.30
- Project Budget Approval Date
- Wed Sep 25 2019
Tender Management
Initiation
- Procuring Entity
- Effia-Kwesimintsim Municipal Assembly
- Procurement Process
- Competitive (National Competitive Tendering)
- Procurement Method
- Open Competitive Tendering
Award
- Number of Firms Tendering
- 4
- Cost Estimate
- GHS 3,315,000.00
Contracting
- Contract Type
- Works
- Contract Title
- Construction Of Storm Drain From Kojo Kumi Avenue, Kwesimintsim Total Filling Station And Kwesimintsim
- Contract Identification
- WR/EKMA/GSCSP/UDG-1/WKS/NCT/02/2020
- Contract Price
- GHS 3,297,752.28
- Contract Scope of Work
- Storm Drain (510 x 6 x 1.5m) Rectangular, Pedestrian Foot Bridge
- Contract Start Date
- Wed Aug 05 2020
- Contract Duration
-
From: Wed Aug 05 2020
To: Fri Feb 19 2021
In Days: 198
| # | Name of Firm | Role |
| 1 |
FINISHERS COMPANY LIMITED |
Lead Contractor |
- Contract Status
-
Active
Project Completion
- Project Status
- Completed
- Completion Cost
- GHS 3,806,639.00
- Completion Date
- Fri Feb 19 2021
- Scope at Completion
- Storm Drain (510 x 6 x 1.5m) Rectangular, Demolition, 0.6 Concrete U Drain Size 0.9m x 0.75m Length 160meters, Approaches and Earth Drain, Box Culvert