Project Identification
- Project Reference Number
- EKMA/DACF/WKS/01/2019
- Project Name
- Construction & Furnishing Of One(1) Community Based Planning Service (Chps) Compound At Adientem (Phase 1)
- Sector
- Health
- Project Type
- New Construction
- Project Location
- Western Region
- Purpose
- TO PROVIDE A HEALTH FACILTY FOR THE PEOPLE OF ADIENTEM AND ITS ENVIRONS.
- Project Description
- CONSTRUCT A BUILDING WHICH IS OWNED BY THE ASSEMBLY WHICH WOULD SERVE AS A PERMANENT ACCOMODATION FOR THE ADIENTEM CHPS COMPOUND
Project Preparation
- Project Scope
- SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE
- Environmental Impact
- IMPROVE THE ACCESS TO QUALITY HEALTH CARE
- Land and Settlement Impact
- IMPROVES THE QUALITY OF HEALTH SERVICE IN THE COMMUNITY AND ITS NEIGHBORING TOWNS
- Design Standard
- NATIONAL BUILDING REGULATION1996 LI 1639,GHANA BUILDING CODE.
- Expected Life of Asset
- 25 YEARS
- Risk Assessment
- NONE
- Funding
-
DACF - Responsiveness Factor Grant
District Assemblies Common Fund (DACF)
GHS 488,241.10
(original amount 93,264.70, currency unrecorded)
- Project Budget
- GHS 488,241.10
- Project Budget Approval Date
- Wed Sep 19 2018
Tender Management
Initiation
- Procuring Entity
- Effia-Kwesimintsim Municipal Assembly
- Procurement Process
- Competitive (National Competitive Tendering)
- Procurement Method
- Open Competitive Tendering
Award
- Number of Firms Tendering
- 5
- Cost Estimate
- GHS 485,000.00
Contracting
- Contract Type
- Consultancy
- Contract Title
- C0nstruction&Furnishing Of One(1) Community Basded Serviced(Chps) Compound At Adientem(Phase 1)
- Contract Identification
- EKMA/DACF/WKS/01/2019
- Contract Price
- GHS 488,241.10
- Contract Scope of Work
- SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE
- Contract Start Date
- Wed Oct 02 2019
- Contract Duration
-
From: Wed Oct 02 2019
To: Mon Nov 01 2021
In Days: 761
| # | Name of Firm | Role |
| 1 |
AMASS ENTERPRISE |
Lead Contractor |
| 2 |
WORKS DEPARTMENT |
Consultant |
- Contract Status
-
Active
Project Completion
- Project Status
- Completed
- Completion Cost
- GHS 488,241.10
- Completion Date
- Mon Nov 01 2021
- Scope at Completion
- SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE