Home / Projects / Construction & Furnishing Of One(1) Comm...
Health Completed

Construction & Furnishing Of One(1) Community Based Planning Service (Chps) Compound At Adientem (Phase 1)

CONSTRUCT A BUILDING WHICH IS OWNED BY THE ASSEMBLY WHICH WOULD SERVE AS A PERMANENT ACCOMODATION FOR THE ADIENTEM CHPS COMPOUND

Western Region EKMA/DACF/WKS/01/2019 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Health
Location
Western Region
Stage
Completion
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 488,241.10
DACF - Responsiveness Factor GrantGHS 488,241.10
ContractGHS 488,241.10
Final CostGHS 488,241.10
Project Identification
Project Reference Number
EKMA/DACF/WKS/01/2019
Project Name
Construction & Furnishing Of One(1) Community Based Planning Service (Chps) Compound At Adientem (Phase 1)
Sector
Health
Project Type
New Construction
Project Location
Western Region
Purpose
TO PROVIDE A HEALTH FACILTY FOR THE PEOPLE OF ADIENTEM AND ITS ENVIRONS.
Project Description
CONSTRUCT A BUILDING WHICH IS OWNED BY THE ASSEMBLY WHICH WOULD SERVE AS A PERMANENT ACCOMODATION FOR THE ADIENTEM CHPS COMPOUND
Project Preparation
Project Scope
SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE
Environmental Impact
IMPROVE THE ACCESS TO QUALITY HEALTH CARE
Land and Settlement Impact
IMPROVES THE QUALITY OF HEALTH SERVICE IN THE COMMUNITY AND ITS NEIGHBORING TOWNS
Design Standard
NATIONAL BUILDING REGULATION1996 LI 1639,GHANA BUILDING CODE.
Expected Life of Asset
25 YEARS
Risk Assessment
NONE
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 488,241.10 (original amount 93,264.70, currency unrecorded)
Project Budget
GHS 488,241.10
Project Budget Approval Date
Wed Sep 19 2018
Tender Management

Initiation

Procuring Entity
Effia-Kwesimintsim Municipal Assembly
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
5
Cost Estimate
GHS 485,000.00

Contracting

Contract Type
Consultancy
Contract Title
C0nstruction&Furnishing Of One(1) Community Basded Serviced(Chps) Compound At Adientem(Phase 1)
Contract Identification
EKMA/DACF/WKS/01/2019
Contract Price
GHS 488,241.10
Contract Scope of Work
SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE
Contract Start Date
Wed Oct 02 2019
Contract Duration
From: Wed Oct 02 2019
To: Mon Nov 01 2021
In Days: 761
#Name of FirmRole
1 AMASS ENTERPRISE Lead Contractor
2 WORKS DEPARTMENT Consultant
Contract Status
Active
Project Completion
Project Status
Completed
Completion Cost
GHS 488,241.10
Completion Date
Mon Nov 01 2021
Scope at Completion
SUB-STRUCTURE (SITE PREPARATION, EXCAVATION AND EARTHWORKS, CONCRETE WORKS); GROUND FLOOR ( CONCRETE WORKS, BLOCK WORKS, JOINERY /IRONMONGRY, PLUMBING WORKS, METAL/GLAZING); SURFACE FURNISHING (TILING, DECORATING, ELECTRICAL INSTALLATION); EXTERNAL WORKS (BOI-DIGESTOR, GROUNDS WORK); PROVISION OF FURNITURE

Questions about this project?

This project is disclosed by Effia-Kwesimintsim Municipal Assembly. Citizens have the right to ask questions about public infrastructure.