Home / Projects / Construction of 1No. 3 Unit Classroom Bl...
Education Completed

Construction of 1No. 3 Unit Classroom Block with Acilliary Facility

1No. 3 Unit Classroom Block with 6 seater toilet Facility

Western Region WR/NEMA/WKS/DACF/RFG/02/2020 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Education
Location
Western Region
Stage
Completion
Contracting Entity
Nzema East Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 252,215.24
DACF - Responsiveness Factor GrantGHS 252,215.24
ContractGHS 504,430.48
Final CostGHS 252,215.24
Project Identification
Project Reference Number
WR/NEMA/WKS/DACF/RFG/02/2020
Project Name
Construction of 1No. 3 Unit Classroom Block with Acilliary Facility
Sector
Education
Project Type
New Construction
Project Location
Western Region
Purpose
The objective of the project was to improve on teaching and learning as well as increase in enrollment
Project Description
1No. 3 Unit Classroom Block with 6 seater toilet Facility
Project Preparation
Project Scope
1No. 3 Unit Classroom Block with 6 seater toilet Facility
Land and Settlement Impact
increase in school enrollment
Design Standard
national building code
Expected Life of Asset
25
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 252,215.24 (original amount 45,038.44, currency unrecorded)
Project Budget
GHS 252,215.24
Project Budget Approval Date
Wed May 27 2020
Tender Management

Initiation

Procuring Entity
Nzema East Municipal Assembly
Procurement Process
National Competitive Tendering (Nct)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 300,000.00

Contracting

Contract Type
Works
Contract Title
Construction Of 1no. 3 Unit Classroom Block With Ancillary At Yedeyesele
Contract Identification
WR/NEMA/WKS/DACF/RFG/02/2020
Contract Price
GHS 252,215.24
Contract Scope of Work
Clearing of site, excavation, hardcore filling, concrete works, block work, roofing, carpentry, joinery, metal works, electrical works, plumbing works, finishing, painting and decorating, external works
Contract Start Date
Fri Jun 05 2020
Contract Duration
From: Fri Jun 05 2020
To: Mon Nov 16 2020
In Days: 164
#Name of FirmRole
1 ICONS 2000 Company Limited Lead Contractor
2 Eric Yeboah Consultant
Contract Status
Completed

Initiation

Procuring Entity
Nzema East Municipal Assembly
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
4
Cost Estimate
GHS 300,000.00

Contracting

Contract Type
Consultancy
Contract Title
Construction Of 1no. 3 Unit Classroom Block With Acilliary At Yedeyesele
Contract Identification
WR/NEMA/WKS/DACF/RFG/02/2020
Contract Price
GHS 252,215.24
Contract Scope of Work
Clearing of site, excavation, hardcore filling, concrete works, block work, roofing, carpentry, joinery, metal works, electrical works, plumbing works, finishing, painting and decorating, external works
Contract Start Date
Fri Jun 05 2020
Contract Duration
From: Fri Jun 05 2020
To: Mon Nov 16 2020
In Days: 164
#Name of FirmRole
1 ICONS 2000 Company Limited Lead Contractor
2 Eric Yeboah Consultant
Contract Status
Active
Contract Implementation

Funds Disbursed

Disbursed: GHS 0.00 Contract value: GHS 504,430.48

Site Photos

Project Completion
Project Status
Completed
Completion Cost
GHS 252,215.24
Completion Date
Mon Nov 16 2020
Scope at Completion
1No. 3 Unit Classroom Block with 6 seater toilet Facility

Questions about this project?

This project is disclosed by Nzema East Municipal Assembly. Citizens have the right to ask questions about public infrastructure.