Provision of Water Facilities in Selected Communities and Construction of Market Shed at Light Industrial Area
Sector
Transport & Roads
Sub sector
Ports & Harbours
Project Type
New Construction
Project Location
Western Region
Purpose
The objective of the project was to ensure that the general public at large get access to potable water in the era of COVID 19 for regular handwashing and other use
Project Description
Provision of Water Facilities in Selected Communities and Construction of Market Shed at Light Industrial Area
Project Preparation
Project Scope
Excavation, back filling, disposal, hardcore, concrete works, reinforcement, form work, block work, plastering, mechanization of borehole, water storage, geological surveying, drilling and construction of borehole, borehole lining and installation, construction of 1no. 5000litres capacity overhead concrete stand
Environmental Impact
Improve Community sanitation
Improve irrigation activities for farming
Land and Settlement Impact
Increased geographical access
Design Standard
Water Resource Commission, Act 522 of 1996
Expected Life of Asset
50
Funding
DACF - Responsiveness Factor GrantDistrict Assemblies Common Fund (DACF)
GHS 252,215.24
(original amount 45,038.44, currency unrecorded)
Provision Of Water Facilities In Selected Communities And Construction Of Market Shed At Light Industrial Area
Contract Identification
WR/NEMA/WKS/DACF/RFG/04/2020
Contract Price
GHS 252,215.24
Contract Scope of Work
Excavation, back filling, disposal, hardcore, concrete works, reinforcement, form work, block work, plastering, mechanization of borehole, water storage, geological surveying, drilling and construction of borehole, borehole lining and installation, construction of 1no. 5000litres capacity overhead concrete stand
Contract Start Date
Fri Jun 05 2020
Contract Duration
From: Fri Jun 05 2020
To: Wed Jul 13 2022
In Days: 768
#
Name of Firm
Role
1
ICONS 2000 Company Limited
Lead Contractor
2
Eric Yeboah
Consultant
Contract Status
Active
Contract Implementation
Variations to Contract
Other
on Fri Jul 31 2020
Why: No Project Change
Funds Disbursed
Disbursed: GHS 0.00Contract value: GHS 252,215.24
Site Photos
Project Completion
Project Status
Completed
Completion Cost
GHS 252,215.24
Completion Date
Mon Jul 13 2020
Scope at Completion
Excavation, back filling, disposal, hardcore, concrete works, reinforcement, form work, block work, plastering, mechanization of borehole, water storage, geological surveying, drilling and construction of borehole, borehole lining and installation, construction of 1no. 5000litres capacity overhead concrete stand