Variations to Contract
Other
on Tue Jan 12 2021
Why: The project location was water log so the substructure was redesigned.
Value / Price Change
on Tue May 24 2022
→ GHS 226,898.20
Why: Change in design
Value / Price Change
on Tue May 24 2022
→ GHS 43,448.10
Why: Change in design
Duration Change
on Tue May 24 2022
End date → Mon Aug 09 2021
Why: Variation in sub-structural works, concrete/block works and compound concreting due to the redesign
Scope Change
on Tue May 24 2022
Why: Due to time spent on sub-structures
Other
on Wed Jul 13 2022
Why: There was no change on the project.
Funds Disbursed
Disbursed: GHS 0.00
Contract value: GHS 183,450.13