Home / Projects / Construction Of Final Floor Of 17 Bay L...
Housing & Buildings Completed

Construction Of Final Floor Of 17 Bay Lockable Stores

Construction of final floor of 17 Bay Lockable Stores with Pavement and Entrance Gate at Kojokrom Market

Western Region WR/STMA/DDF/WKS/NCT/01/2019 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Housing & Buildings
Location
Western Region
Stage
Completion
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 521,702.55
DACF - Responsiveness Factor GrantGHS 521,702.55
ContractGHS 520,281.10
Final CostGHS 520,281.10
Project Identification
Project Reference Number
WR/STMA/DDF/WKS/NCT/01/2019
Project Name
Construction Of Final Floor Of 17 Bay Lockable Stores
Sector
Housing & Buildings
Project Type
New Construction
Project Location
Western Region
Purpose
The project will serve as market facility which will enhance buying and selling activity in the market.
Project Description
Construction of final floor of 17 Bay Lockable Stores with Pavement and Entrance Gate at Kojokrom Market
Project Preparation
Project Scope
Construction of 17 Bay Lockable Stores with Pavement and Entrance Gate at Kojokrom Market
Environmental Impact
The project will serve as a market facility which will enhance buying and selling activity in the market.
Land and Settlement Impact
The project will enhance marketing activities
Design Standard
Ghana Building Code
Expected Life of Asset
30 years
Risk Assessment
N/A
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 521,702.55 (original amount 97,151.30, currency unrecorded)
Project Budget
GHS 521,702.55
Project Budget Approval Date
Thu Feb 14 2019
Contact Details
info@stma.gov.gh
Tender Management

Initiation

Procuring Entity
Sekondi-Takoradi Metropolitan Assembly
Procuring Entity Contact Details
info@stma.gov.gh
Procurement Process
Competitive (National Competitive Tendering)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
4
Cost Estimate
GHS 525,500.55

Contracting

Contract Type
Works
Contract Title
Construction Of 17 Bay Lockable Stores With Pavement And Entrance Gate At Kojokrom Market
Contract Identification
WR/STMA/DDF/WKS/NCT/01/2019
Contract Price
GHS 520,281.10
Contract Scope of Work
Construction of 17 Bay Lockable Stores with Pavement and Entrance Gate at Kojokrom Market
Contract Start Date
Sat Sep 12 2020
Contract Duration
From: Sat Sep 12 2020
To: Mon Mar 29 2021
In Days: 198
#Name of FirmRole
1 JOBS ENGINEERING AND BUILDING CONST. WORKS Lead Contractor
2 STMA WORKS DEPARTMENT Consultant
Contract Status
Completed
Contract Implementation

Variations to Contract

Other on Tue Jul 12 2022
Why: There was no change on the project

Funds Disbursed

Disbursed: GHS 0.00 Contract value: GHS 520,281.10

Site Photos

Project Completion
Project Status
Completed
Completion Cost
GHS 520,281.10
Completion Date
Mon Mar 29 2021
Scope at Completion
Construction of 17 Bay Lockable Stores with Pavement and Entrance Gate at Kojokrom Market

Audit & Evaluation Reports

TypeDateAuditor / EvaluatorFindings
Quality Assurance 01 Jul 2022 An audit was conducted on the project but there were no adverse. (Auditor General's Report - 2021)

Questions about this project?

This project is disclosed by Sekondi-Takoradi Metropolitan Assembly. Citizens have the right to ask questions about public infrastructure.