Home / Projects / Construction Of Out-Patient Department B...
Health Completed

Construction Of Out-Patient Department Block

Out-Patient Department Block

Western Region WEDA/WR/DACF/OPDB/01/19 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Health
Location
Western Region
Stage
Completion
Contracting Entity
Wassa East District Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 329,965.65
District Assemblies Common FundGHS 329,965.65
ContractGHS 329,965.65
Project Identification
Project Reference Number
WEDA/WR/DACF/OPDB/01/19
Project Name
Construction Of Out-Patient Department Block
Sector
Health
Project Type
New Construction
Project Location
Western Region
Purpose
Health Delivery Improvement
Project Description
Out-Patient Department Block
3 Good Health and Well-Being
Project Preparation
Project Scope
Male & Female Ward, Consulting Room, Waiting Area, Records Room/Revenue, Storage, Washrooms and Pharmacy
Land and Settlement Impact
N/A
Design Standard
National Building Regulation( LI 1630), Ghana Building Codes
Expected Life of Asset
20 Years
Risk Assessment
None
Funding
District Assemblies Common Fund District Assemblies Common Fund (DACF)
GHS 329,965.65 (original amount 54,994.28, currency unrecorded)
Project Budget
GHS 329,965.65
Project Budget Approval Date
Fri Oct 25 2019
Contact Details
info@weda.gov.gh
Tender Management

Initiation

Procuring Entity
Wassa East District Assembly
Procuring Entity Contact Details
info@weda.gov.gh
Procurement Process
Competitive Tendering (Nct)
Procurement Method
Selective / Restricted Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 325,000.00

Contracting

Contract Type
Works
Contract Title
Construction Of 1no. Out-Patient Department Block At Atobiase
Contract Identification
WEDA/WKS/009/19
Contract Price
GHS 329,965.65
Contract Scope of Work
Male & Female Ward, Consulting Room, Waiting Area, Records Room/Revenue, Storage, Washrooms and Pharmacy
Contract Start Date
Thu Nov 14 2019
Contract Duration
From: Thu Nov 14 2019
To: Tue Apr 14 2020
In Days: 152
Contract Status
Active
Contract Implementation

Variations to Contract

Duration Change on Sat Jun 25 2022
End date → Fri Sep 23 2022
Why: Delay release of funds

Funds Disbursed

Disbursed: GHS 0.00 Contract value: GHS 329,965.65

Site Photos

Project Completion
Project Status
Completed
Completion Date
Tue Apr 14 2020
Scope at Completion
Male & Female Ward, Consulting Room, Waiting Area, Records Room/Revenue, Storage, Washrooms and Pharmacy

Audit & Evaluation Reports

TypeDateAuditor / EvaluatorFindings
Quality Assurance 31 Dec 2021 Audit report
Quality Assurance 31 Dec 2021 Delayed project

Questions about this project?

This project is disclosed by Wassa East District Assembly. Citizens have the right to ask questions about public infrastructure.