Home / Projects / Construction of a 900mm U-drain with Sla...
Transport & Roads Completed

Construction of a 900mm U-drain with Slab,and 1.5m Rectangular Drain

Western Region CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Transport & Roads
Location
Western Region
Stage
Completion
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 941,737.00
Agence Française de DéveloppementEUR 156,956.00
ContractGHS 941,737.00
Final CostGHS 941,737.00
Project Identification
Project Reference Number
Project Name
Construction of a 900mm U-drain with Slab,and 1.5m Rectangular Drain
Sector
Transport & Roads
Sub sector
Roads
Project Type
New Construction
Project Location
Western Region
Purpose
help the flow of water.
Project Description
Construction of a 900mm U-drain with Slab,and 1.5m Rectangular Drain
6 Clean Water and Sanitation
Project Preparation
Project Scope
n/a
Environmental Impact
n/a
Land and Settlement Impact
n/a
Design Standard
standard
Expected Life of Asset
50
Risk Assessment
n/a
Funding
Agence Française de Développement Donor / Development Partner
EUR 156,956.00 (GHS 941,737.00 at time of funding)
Project Budget
GHS 941,737.00
Project Budget Approval Date
Wed Feb 20 2019
Contact Details
info@stma.gov.gh
Tender Management

Initiation

Procuring Entity
Sekondi-Takoradi Metropolitan Assembly
Procuring Entity Contact Details
info@stma.gov.gh
Procurement Process
National Competitive Tendering
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
10
Cost Estimate
GHS 991,737.00

Contracting

Contract Type
Works
Contract Title
Construction Of A 900mm U-Drain With Slab,And 1.5m Rectangular Drain
Contract Identification
N/A
Contract Price
GHS 941,737.00
Contract Scope of Work
Construction of a 900mm U-drain with Slab,and 1.5m Rectangular Drain
Contract Start Date
Wed Feb 20 2019
Contract Duration
From: Wed Feb 20 2019
To: Tue Apr 30 2019
In Days: 69
#Name of FirmRole
1 Dagbene Borns Company Ltd Lead Contractor
Contract Status
Completed
Project Completion
Project Status
Completed
Completion Cost
GHS 941,737.00
Completion Date
Tue Apr 30 2019
Scope at Completion
It has been completed

Questions about this project?

This project is disclosed by Sekondi-Takoradi Metropolitan Assembly. Citizens have the right to ask questions about public infrastructure.