Home / Projects / Construction Of One (1) No. 30 Bay Parti...
Housing & Buildings Completed

Construction Of One (1) No. 30 Bay Partitioned Market Shed At East Tanokrom

Western Region EKMA/DDF/RFQ/WKS/ CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Housing & Buildings
Location
Western Region
Stage
Completion
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 198,482.50
DACF - Responsiveness Factor GrantGHS 198,482.50
ContractGHS 198,482.52
Final CostGHS 198,482.50
Project Identification
Project Reference Number
EKMA/DDF/RFQ/WKS/
Project Name
Construction Of One (1) No. 30 Bay Partitioned Market Shed At East Tanokrom
Sector
Housing & Buildings
Project Type
New Construction
Project Location
Western Region
Purpose
Improves the standard of living of farmers and the locals
Project Description
Construction of one (1) NO. 30 Bay Partitioned Market Shed at East Tanokrom
8 Decent Work and Economic Growth
Project Preparation
Project Scope
Demolition and alteration, Sub-structure, In-situ concrete/Large precast concrete, Masonry,Structural/ Carcassing metal/timber, Cladding/Covering, Surface finishes, Painting, Mechanical and Electrical Services.
Environmental Impact
none
Land and Settlement Impact
helps in the buying and selling of goods and services
Design Standard
National Building Regulation 1996 LI 1639 Ghana Building Code
Expected Life of Asset
30 years
Risk Assessment
none
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 198,482.50 (original amount 36,087.70, currency unrecorded)
Project Budget
GHS 198,482.50
Project Budget Approval Date
Thu Oct 29 2020
Tender Management

Initiation

Procuring Entity
Effia-Kwesimintsim Municipal Assembly
Procurement Process
Request For Quotation (Rfq)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
2
Cost Estimate
GHS 198,482.52

Contracting

Contract Type
Works
Contract Title
Construction of One (1) No. 30 Bay Partitioned Market Shed At East Tanokrom
Contract Price
GHS 198,482.52
Contract Scope of Work
Demolition and alteration, Sub-structure, In-situ concrete/ Large precast concrete, Masonry, Structural/Carcassing metal/timber, Cladding/Covering, Surface finishes, Painting, Mechanical and Electrical services
Contract Start Date
Thu Nov 12 2020
Contract Duration
From: Thu Nov 12 2020
To: Fri Mar 12 2021
In Days: 120
Contract Status
Tendered
Project Completion
Project Status
Completed
Completion Cost
GHS 198,482.50
Completion Date
Fri Mar 12 2021
Scope at Completion
Demolition and alteration, Sub-structure, In-situ concrete/Large precast concrete, Masonry,Structural/ Carcassing metal/timber, Cladding/Covering, Surface finishes, Painting, Mechanical and Electrical Services.

Questions about this project?

This project is disclosed by Effia-Kwesimintsim Municipal Assembly. Citizens have the right to ask questions about public infrastructure.