Home / Projects / Construction Of Cassava Processing Centr...
Housing & Buildings Completed

Construction Of Cassava Processing Centre

Construction of Cassava Processing Centre at Bokro

Western Region CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Housing & Buildings
Location
Western Region
Stage
Completion
Contracting Entity
Nzema East Municipal Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 382,263.00
DACF - Responsiveness Factor GrantGHS 382,263.00
ContractGHS 382,263.00
Final CostGHS 382,263.00
Project Identification
Project Reference Number
Project Name
Construction Of Cassava Processing Centre
Sector
Housing & Buildings
Project Type
New Construction
Project Location
Western Region
Purpose
Processing of Cassava for Local Consumption
Project Description
Construction of Cassava Processing Centre at Bokro
8 Decent Work and Economic Growth 9 Industry, Innovation and Infrastructure
Project Preparation
Project Scope
Cassava Milling Machine, Stove, Chimney, Offices
Environmental Impact
Yes
Land and Settlement Impact
N/A
Design Standard
N/A
Expected Life of Asset
20 years
Risk Assessment
N/A
Funding
DACF - Responsiveness Factor Grant District Assemblies Common Fund (DACF)
GHS 382,263.00 (original amount 76,452.60, currency unrecorded)
Project Budget
GHS 382,263.00
Project Budget Approval Date
Fri Oct 27 2017
Tender Management

Initiation

Procuring Entity
Nzema East Municipal Assembly
Procurement Process
International Competitive Tendering (Ict)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 350,000.00

Contracting

Contract Type
Works
Contract Title
Construction Of State Of The Art Cassava Processing Factory
Contract Identification
WR/NEMA/WKS/DDF/01/2018
Contract Price
GHS 382,263.00
Contract Scope of Work
General Works and Mechanical Installation
Contract Start Date
Sat Feb 16 2019
Contract Duration
From: Sat Feb 16 2019
To: Sun Jan 05 2020
In Days: 323
Contract Status
Active
Project Completion
Project Status
Completed
Completion Cost
GHS 382,263.00
Completion Date
Tue Jan 05 2021
Scope at Completion
Cassava Milling Machine, Stove, Chimney, Offices

Questions about this project?

This project is disclosed by Nzema East Municipal Assembly. Citizens have the right to ask questions about public infrastructure.