The overall objective of the project is to expand infrastructural facilities within kokompe industrial enclave to create the necessary environment for growth of economic activities in the Metropolis.
The project is expected to provide the necessary facilities required for the sustained growth of activities within the industrial estate as well as provide for sound environmental practices. enclave by constructing model garages, skill training centre to upgrade their skills, road upgrading and expand social amenities to improve the working environment to create more jobs.
Project Description
Construction of 25 No. Garages and Two-Storey Skills & Training Centre
5
Gender Equality
Project Preparation
Project Scope
Construction of 25 No. Garage Units
Construction of Skills and Training Centre
Construction of Flush Toilet and Shower
Power and Water Supply
Environmental Impact
There was an environmental impact assessment which identified potential impacts on the physical, biological and socio-economic/cultural environments, occupational safety, health and welfare of the employees.
Land and Settlement Impact
N/A
Design Standard
The various building components shall be incorporated in the building design according to National Building Regulations, (MWH, 1996) which entails: Building Location, Building Orientation, Spatial Requirements and Floor Area Ratio (FAR), Building Fabric and Components, Air Movement and Ventilation, Accessibility and Means of Escape, General Services
Expected Life of Asset
30
Risk Assessment
N/A
Funding
Agence Française de DéveloppementDonor / Development Partner
EUR 1,079,684.21
(GHS 3,454,989.45 at time of funding)
Construction Of 25 No. Garages And Two-Storey Skills & Training Centre
Contract Identification
MLGRD/GUMPP/STMA/WKS/ICT/101/UKE/LOT3
Contract Price
GHS 3,454,989.45
Contract Scope of Work
- Construction of 25 No. Garage Units
- Construction of Skills and Training Centre
- Construction of Flush Toilet and Shower
- Power and Water Supply
Contract Start Date
Mon Jan 05 2015
Contract Duration
From: Mon Jan 05 2015
To: Fri Feb 10 2017
In Days: 767
#
Name of Firm
Role
1
Hydronomics Limited
Lead Contractor
2
Lamda Consult Limited
Consultant
Contract Status
Completed
Contract Implementation
Variations to Contract
Duration Change
on Fri Mar 26 2021
End date → Tue Feb 28 2017 Why: Duration changes: The was issues with land management and re-organisation of the place for the new facility be constructed