Home / Projects / Ketan Classroom Block
Education Completed

Ketan Classroom Block

Six classroom unit with office and store

Western Region WR/STMA/ED/2026/001 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Education
Location
Western Region
Stage
Identification
Publication DateWed Jul 08 2026
Disclosed Values
BudgetGHS 1,250,000.00
ContractGHS 1,265,000.00
Final CostGHS 1,272,400.00
Physical Progress48%
Project Identification
Project Reference Number
WR/STMA/ED/2026/001
Project Name
Ketan Classroom Block
Sector
Education
Project Type
New Construction
Project Location
Western Region
Purpose
Improve access to basic education
Project Description
Six classroom unit with office and store
4 Quality Education 6 Clean Water and Sanitation
Project Preparation
Project Scope
Six classrooms, office, store and 4-seater KVIP
Environmental Impact
Minimal
Social Impact
Improved enrolment
Land and Settlement Impact
School-owned land, no resettlement
Design Standard
GES standard design
Expected Life of Asset
30 years
Risk Assessment
Low flood risk
Project Budget
GHS 1,250,000.00
Project Budget Approval Date
Tue Feb 10 2026
Contact Details
info@stma.gov.gh
Tender Management

Initiation

Procuring Entity
Sekondi-Takoradi Metropolitan Assembly
Procuring Entity Contact Details
info@stma.gov.gh
Procurement Process
National Competitive Tendering per PPA Act 663
Procurement Method
Open Competitive Tendering
Process Description
Main construction works package

Award

Number of Firms Tendering
2
Cost Estimate
GHS 1,200,000.00
Tender Period
Fri May 01 2026 → Mon Jun 15 2026
Award Date
Tue Jun 30 2026
Award Criteria
Lowest evaluated responsive bid

Contracting

Contract Administrative Entity
Sekondi-Takoradi Metropolitan Assembly
Contract Type
Works
Contract Title
Construction of 6-Unit Classroom Block — Main Works
Contract Identification
STMA/WKS/2026/012
Contract Price
GHS 1,265,000.00
Contract Scope of Work
Full construction per BoQ and drawings
Contract Start Date
Wed Jul 15 2026
Contract Duration
From: Wed Jul 15 2026
To: Thu Oct 14 2027
In Days: 456
#Name of FirmRole
1 Takoradi Roads Limited Lead Contractor
Contract Status
Active
Contract Implementation

Variations to Contract

Value / Price Change on Thu Oct 15 2026
GHS 1,150,000.00 → GHS 1,265,000.00
Why: Rock excavation encountered at foundation level requiring blasting
Duration Change on Sun Nov 01 2026
End date Wed Jul 14 2027 → Thu Oct 14 2027
Why: Extension of time due to rock blasting delays
Scope Change on Sun Nov 15 2026
Why: Additional classroom furniture scope
Scope Change on Mon Nov 16 2026
Why: Furniture variation round 2

Funds Disbursed

Disbursed: GHS 345,000.00 Contract value: GHS 1,265,000.00

Progress over Time

Site Photos

Project Completion
Project Status
Completed
Completion Cost
GHS 1,272,400.00
Variation Order No. 1 added GHS 115,000
Completion Date
Sat Nov 20 2027
4-month extension due to rock excavation
Scope at Completion
As designed plus rock blasting works
Scope unchanged except foundation redesign
Reasons for Project Changes
Unforeseen ground conditions at foundation level
Operations & Maintenance
Maintenance Plan
Annual
Jobs Generated
10
Decommissioning
Decommission Date
Mon Jan 01 2057
Disposal Method
Transfer to Another Entity
Receiving Entity
Sekondi-Takoradi Metropolitan Assembly
Decommission Plan
Transfer to community
Decommission Cost
GHS 5,000.00
Environmental Remediation
Site restoration
Carbon Savings
Timber reuse
Sustainability

Social

Land Compensation Budget
GHS 12,000.00
On Indigenous Land
Yes: Stool land, chief consented

Environment & Climate

Impact Category
Category B
In Protected Area
No
Conservation Measures
Replant 20 trees
Abatement Cost
GHS 3,000.00
Greenhouse Gas Forecast
Negligible

Other Sustainability Indicators

DimensionIndicatorValue
Social Sustainability localJobsCreated 8.00
Climate Finance
Climate Objective
Adaptation
Financial Instrument
Grant
Amount of Investment
GHS 50,000.00
Ratio of Co-finance
0.4000
Carbon Footprint
Low embodied carbon
Impact Measurement
Annual GHG audit
Published Documents
DocumentTypePublished
Preparation
Feasibility Study Feasibility Study / Project Brief 20 Jan 2026 Download
Completion
Project Completion Report Project Completion Report 01 Dec 2027 Download

Questions about this project?

This project is disclosed by Sekondi-Takoradi Metropolitan Assembly. Citizens have the right to ask questions about public infrastructure.